所属地区: --
所属机构: --
抱歉,该信息暂无中文翻译信息,为您显示项目原文信息。
Published date: 6 June 2024
Last edited date: 2 July 2024
Open opportunity - This means that the contract is currently active, and the buying department is looking for potential suppliers to fulfil the contract.
Construction work - 45000000
England
£3,750,000
GLOSCC001-DN722873-63268655
6 June 2024
16 July 2024
11:59pm
9 September 2024
15 August 2025
Works
Open procedure (below threshold)
Any interested supplier may submit a tender in response to an opportunity notice.
This procedure can be used for procurements below the relevant contract value threshold.
Yes
No
This advert is intended to notify potential suppliers of the tender for the A435 Cycleway Section 2.1 & Wellington Road scheme.
The A435 Cycleway Section 2.1 works are located between the GWSR Bridge and Bishop's Cleeve roundabout, with the Wellington Road works located between Wellington Road and Central Cross Drive.
The works are located at two distinct sites. The first site, A435 Cycleway Section 2.1, is located north of the GWSR Bridge (approx. post code GL50 4SH) to Bishops Cleeve Roundabout (approx. post code GL52 8SF), and the second site, Wellington Road, located from Wellington Road Junction (approx. post code GL52 2AH) to Central Cross Drive junction (approx. post code GL52 2AH). This scheme is part of a wider strategic scheme to boost active travel provision within the county, through the creation of the Gloucestershire Cycle Spine. The overall scheme will implement a continuous cycleway for cyclists of all ages and abilities between the main hubs of Bishops Cleeve, Cheltenham, Gloucester, Haresfield and Stroud. In addition, this scheme will also install a section of sheet piling along the A435, which shall improve embankment stability and reduce continuous carriageway cracking.
The client is looking for a Principal Contractor to deliver the construction phase of this scheme.
Summary of Construction Phase key deliverables are as follows:
Provide suitable Traffic Management during the construction works.
Pedestrian access to residents always during the construction works.
Utility diversion works (arranged by GCC for PC to liaise/accommodate).
New drainage works and tie-in to existing.
A mixture of Highway, segregated footway / cycleway track and new shared use path construction.
Junction and carriageway realignments.
New traffic signals facilities across the route.
Streetlighting column installation and relocation.
Sheet piling installation along the A435 for 160m.
A summary of the outline programme is shown below:
Tender return: 16th July 2024
Award: Friday 9th August 2024
Anticipated Works Start Date: 9th September 2024
Completion: 15th August 2025
Overall Duration: 39 weeks
Indicative Value: £3.75m (£4.5m including VAT)
The proposed procurement route will be a single stage (Open Procedure) using the NEC4 ECC form of Contract, Option A Priced Contract with Activity Schedule.
Full details will be available in the tender pack om Procontract.
https://procontract.due-north.com/Advert?advertId=f2a5e8b6-9d0c-ef11-812b-005056b64545&p=696a9836-1895-e511-8105-000c29c9ba21
A435 Cycleway Section 2.1 & Wellington Road
Follow the instructions given in the description or the more information section.
Mike McGowan
Shire Hall
Gloucester
GL1 2TH
England
+44 1452328900
mike.mcgowan@gloucestershire.gov.uk
Is there anything wrong with this page?
本网站为您提供准确和及时的招投标信息,但招投标信息存在着变更的可能,请您务必在交易前向招标代理机构或招标人咨询投标详细要求,有关招标的具体要求及情况以招标代理机构或招标人的解释为准。
如果您对这篇招标信息有任何补充或修改建议,请告知我们。
猜你喜欢